DNR issues notice of violation to Enbridge

13 October 2026 at 23:41

A billboard promoting Enbridge Inc. (Susan Demas | Michigan Advance)

The Wisconsin Department of Natural Resources issued a notice of violation to the Enbridge Energy Company for incidents in Iron and Ashland counties, where the company is working on a controversial reroute of its Line 5 oil and gas pipeline. 

The notice includes violations of permit conditions of the reroute construction project, and violations of state environmental laws for the unpermitted construction of a bypass around the Saxon Line 5 spill site. It covers laws involving state water quality, wetlands, navigable waterways, air quality, storm water and endangered resources protection.

The violations are alleged to have occurred from March 30 through Sept. 21 of this year. In August, a section of the pipeline leaked natural gas liquid near the town of Saxon, with drone video of the leak showing plumes of smokey vapor pouring out of an area where trucks and equipment were parked. Enbridge said that the leak occurred when an unoccupied truck rolled over an open excavation site near a valve project. Environmental groups fear that the leak could have been the largest of its kind in Wisconsin history.

 

 

The violation notice sets an enforcement conference, which is a standard step where the DNR and Enbridge will discuss the alleged violations. After the conference, the DNR can take further enforcement action such as issuing citations, referring the case to the Wisconsin Department of Justice for prosecution to seek forfeitures, or other court-related actions. 

A DNR press release notes that the notice of violation is separate from Enbridge’s responsibility under the spills law to respond to hazardous substances which may have been released during the August leak.

“These allegations are numerous and serious,” said Clean Wisconsin Attorney Evan Feinauer in a statement. “The DNR must now use the full force of its enforcement authority to hold Enbridge accountable and secure relief that addresses the significant harm to our environment Enbridge has caused.”

This article was updated with comment from Clean Wisconsin.

Enbridge breaches aquifer along Line 5 reroute path

6 October 2026 at 07:48
Laina G. Stebbins

Laina G. Stebbins

An aquifer breach has occurred in northern Wisconsin, along the reroute path of the Enbridge Line 5 oil and gas pipeline. In a statement, Enbridge spokesperson Juli Kellner said that “a flow of water was observed following the direct installation of pipe beneath the Marengo River.”

Kellner said that Enbridge is working with the Department of Natural Resources “and other engineering and environmental specialists to determine next steps.” The breach was first reported by Northern News Now.

It’s unclear how much water was released due to the breach. The DNR didn’t respond to requests for comment. 

In August, a section of Line 5 released more than 1.3 million gallons of natural gas liquid after an unoccupied truck rolled and damaged the pipeline. WPR reported that the leak was the largest of its kind for both Enbridge and the state of Wisconsin. 

Enbridge previously  breached an aquifer while building the Line 3 pipeline in Minnesota. The breach led to an uncontrolled release of hundreds of millions of gallons of groundwater. Minnesota’s attorney general filed charges against the company in that case. 

Line 5 is a decades-old pipeline that carries up to 23 million gallons of crude oil and natural gas liquids daily from Ontario to the southern Unites States. In 2019, the Bad River Band of Lake Superior Chippewa sued Enbridge to shut the pipeline down and to expel the Canadian-owned company from tribal lands. 

Enbridge has since begun work on rerouting Line 5 around the reservation, a move that has been contested by tribal communities and environmental groups as endangering ecosystems and natural resources. Legal battles over the pipeline’s future continue in federal court. Advocates have called on the Wisconsin DNR to revoke the permits granted to Enbridge to carry out the reroute.

On Tuesday, a DNR spokesperson sent an emailed statement to Wisconsin Examiner, stating that the state agency is monitoring the groundwater release. The breach occurred during the installation of a new section of pipeline. The spokesperson added that the area’s hydrology is complex and that “it is unknown if this event is caused by a aquifer breach. The flow rate for the release is 5% of the flow rates of confirmed aquifer breaches in other states involving similar projects.

This article was updated with comment from the Department of Natural Resources.

 

Line 5 reopens after spill despite DNR warning

15 September 2026 at 19:06
Laina G. Stebbins

Laina G. Stebbins

The Line 5 oil and natural gas pipeline across northern Wisconsin went back online Monday, three weeks after a broken valve caused 1.3 million gallons of natural gas liquids to spill into the nearby Iron County town of Saxon, the pipeline’s operator Enbridge said in a news release. 

The spill occurred Aug. 25 when a truck rolled forward and broke the valve as crews worked on the controversial reroute of Line 5’s path across the state from Canada. Enbridge immediately began working to bypass the broken valve and get the pipeline back up and running despite warnings from the state Department of Natural Resources that it was doing that construction without the proper permitting. 

The DNR issued a notice of noncompliance to Enbridge last week ordering it to halt its work. Despite that warning, Enbridge completed the work and said in its news release that “work continues at the site focused on safe access, environmental testing and remediation.” The company said it has worked closely with federal and local agencies to protect health and safety and that “we continue to work” with the DNR on the “relevant permitting and separately on environmental conditions at the incident site.” 

“Ongoing environmental monitoring at the site continues,” Enbridge stated. “Wildlife has not been impacted. Testing of surface water and from a nearby residential well continues to show no impacts. Water monitoring wells continue to show no contamination. Soil and water monitoring are in place, as are plans to test, remove and properly dispose of the soil in the trench.”

Since the spill, the company has argued it needs to get the pipeline back up and running as soon as possible because the fossil fuels it transports are too important. 

“Line 5 is critical infrastructure, securely supplying 10 refineries and propane production facilities that deliver energy to millions of people in the Midwest and Great Lakes regions,” the company news release states. 

Meanwhile, environmental activists, members of the Bad River Band of Lake Superior Chippewa and elected officials have continued to argue that the spill is confirmation that the pipeline has always been a risk to Wisconsin’s environment and should be permanently shut down.

Wisconsin DNR tells Enbridge to stop work on pipeline after natural gas leak

10 September 2026 at 21:52
Laina G. Stebbins

Laina G. Stebbins

The Wisconsin Department of Natural Resources has told the oil and gas company Enbridge to halt construction on the Line 5 pipeline across northern Wisconsin after a massive spill of natural gas liquids in Iron County late last month. 

The spill, which occurred near the town of Saxon and at 1.3 million gallons of natural gas liquids was the largest in the company’s history, was caused when an unoccupied truck rolled over a valve while crews were doing construction work. The company is in the process of rerouting Line 5 off the Bad River tribe’s reservation — a controversial project which has triggered numerous challenges to the DNR and federal permits. 

Since the spill, environmental activists, tribal members, candidates for office and elected officials in both Wisconsin and Michigan have renewed their calls for the pipeline to be shut down. 

After the spill, Enbridge began working to bypass the damaged valve so the pipeline could again be used to transport Canadian oil and gas. On Wednesday, the DNR issued a notice of noncompliance to the company, noting that Enbridge was constructing the bypass without the proper permits from the DNR. 

In the notice, and in an accompanying letter from DNR Secretary Karen Hyun, the agency said that it had told the company on three separate occasions it could not conduct the bypass work without approval from the state, and possibly from both the county and federal governments. 

The notice states that the bypass construction involves matting placed in nearby wetlands and close to Spoon Creek, which is considered a navigable waterway regulated by state law. 

In her letter, Hyun said she was “deeply concerned and incredibly frustrated” by Enbridge’s actions, especially the potentially harmful effects caused by the “significant discharge” of pollutants known as volatile organic compounds — which can be harmful to people’s health and the local environment. 

“Enbridge has continued to add to the growing list of environmental concerns and violations, demonstrating disregard for the environment, human health, and the statutory authority of the department,” she wrote. “Regarding the Line 5 reroute construction, Enbridge has caused additional discharges to the environment since my earlier letter, which have caused continued frustration and profound unease for the department and the people of Wisconsin. Additionally, at the location of the Line 5 Natural Gas Liquids (NGL) spill on August 25, Enbridge has made the decision to start unpermitted construction of a bypass, despite the extensive efforts of the DNR to educate Enbridge on the necessary permits and approvals for this bypass construction and a commitment to review submitted materials in a timely matter. Based on this pattern of noncompliance demonstrated by Enbridge, my concern over the environmental impacts of Enbridge’s activities over the past weeks has only heightened.”

In a statement, Enbridge spokesperson Juli Kellner said the company is working “around the clock” to clean up the spill site and return the pipeline to service. 

“Enbridge continues working towards both priorities related to the third-party line strike near Saxon, Wis. — the safe control and remediation of the incident site and completing a temporary bypass to allow the pipeline to return to service, which will help resolve energy supply disruptions,” she said. “Around the clock work on both priorities is being done in parallel. Line 5 is critical infrastructure delivering energy to millions of people in the Midwest and Great Lakes regions. We continue to work with the Wisconsin DNR on relevant permitting and separately on environmental conditions at the incident site.”

Rob Lee, an attorney for Midwest Environmental Advocates who has worked on the challenges to Enbridge’s Line 5 permits, said that the company doesn’t get to decide that restoring the pipeline is more important than following state law. 

“Enbridge knew it needed authorization before it started this work. The DNR told the company that repeatedly. Enbridge went ahead anyway. That shows extraordinary disregard for Wisconsin’s environmental laws and for the state agency charged with enforcing them,” Lee said. ““Enbridge cannot simply decide that getting Line 5 back in service is more important than following Wisconsin law. They’ve been out there moving earth, crossing waterways and disturbing wetlands without permits. They need to stop treating environmental requirements as obstacles to work around and start following the law. If they don’t, DNR should revoke the permits for the reroute.”

❌
❌