Enbridge says another fire destroys drill rig on Line 5 project in northern Wisconsin

An aerial view of a fenced construction site surrounded by trees shows smoke in the air, charred machinery, a yellow excavator, stacked pipes, trucks and several people.
Reading Time: 2 minutes

Enbridge said an early morning fire destroyed a drill rig and support equipment on a $1 billion project to reroute its Line 5 oil and gas pipeline in northern Wisconsin.

In a statement, Enbridge spokesperson Juli Kellner called the fire that damaged a horizontal directional drill rig and related equipment an act of vandalism. She said there was also graffiti found at the site. No details were provided on where the fire took place, but Kellner said no injuries were reported.

Iron County Sheriff Paul Samardich confirmed the blaze occurred in Ashland County. The Ashland County Sheriff’s Office did not immediately respond to requests for additional details on the fire.

The incident follows two other fires targeting Enbridge that occurred last month, including a blaze in Ashland County that destroyed a drill rig on the Line 5 reroute.

“This is the second major vandalism involving construction equipment on the project,” Kellner said. “These incidents put the local community, landowners, first responders and our workers at risk and result in environmental impacts.”

The FBI and the federal Bureau of Alcohol, Tobacco, Firearms and Explosives, or ATF, are investigating the cause of the two previous fires that occurred in the town of Gingles and the city of Superior. Representatives of the FBI and ATF did not immediately respond to requests for comment.

Kellner said Enbridge supports people’s rights to express their views “legally and peacefully.”

“Acts that damage property and put people or the environment at risk are neither legal nor peaceful,” Kellner said. “We take these incidents very seriously and will cooperate fully with authorities as they investigate and seek to hold those responsible accountable.”

Enbridge’s Line 5 pipeline carries up to 23 million gallons of oil and natural gas liquids daily from Superior to Sarnia, Ontario, serving 10 refineries and propane facilities in the Great Lakes region.

The fires come after an Aug. 25 gas leak on Line 5 in the town of Saxon released more than 1.3 million gallons of natural gas liquids into the atmosphere. Preliminary findings suggest a subcontractor’s truck was in neutral when it rolled into an open construction trench, striking the pipeline. No one was injured in the incident, and response to the spill is still ongoing.

Following the leak, the Wisconsin Department of Natural Resources asked Enbridge to halt work on a temporary bypass around the site of the leak, saying the company lacked necessary approvals.

On Sept. 28, Enbridge also reported a release of groundwater at a site where crews were directly installing pipe underneath the Marengo River. It was initially reported as an aquifer breach, and the DNR has since said it’s still investigating the source of the release and determining any negative effects to groundwater.

This story was originally published by WPR.

Enbridge says another fire destroys drill rig on Line 5 project in northern Wisconsin is a post from Wisconsin Watch, a non-profit investigative news site covering Wisconsin since 2009. Please consider making a contribution to support our journalism.

Enbridge estimates northern Wisconsin Line 5 gas leak will cost $15M

Aerial view of a work site with vehicles, equipment and a large white-covered structure beside fields and trees
Reading Time: 3 minutes

A report filed with federal regulators estimates an August gas leak on Enbridge’s Line 5 oil and gas pipeline in northern Wisconsin will cost at least $15.1 million.

An accident report filed by Enbridge Energy Limited Partnership Thursday with the federal Pipeline and Hazardous Materials Safety Administration shows emergency response makes up the bulk of the costs, estimated at nearly $9.9 million.

The company estimated public and private property damage and repairs at about $5 million. Environmental remediation and lost product account for the remainder of the estimated expenses.

Enbridge has said the leak occurred after a subcontractor’s unoccupied flatbed truck rolled into an open excavation site for a Line 5 valve project in Iron County, striking and puncturing the pipeline.

“The affected pipeline section was immediately isolated, and Line 5 was shut down. No injuries occurred, and one nearby rural residence was evacuated as a precaution,” wrote Stacy Soine, Enbridge’s regulatory compliance advisor.

The company told regulators about 33,000 barrels, or more than 1.3 million gallons, of natural gas liquids escaped during the incident. Most has not been recovered because propane and butane vaporized upon release. The company recovered 165 barrels from the trench with a vacuum truck.

The report sheds no new light on how the truck rolled into the trench, saying the cause remains under investigation. But WPR obtained a corrective action order issued by the Pipeline and Hazardous Materials Safety Administration, or PHMSA, that states preliminary findings indicate “the tractor trailer was left temporarily unattended and placed in neutral transmission on a gradient slope prior to the failure.”

Enbridge told PHMSA it shut down the pipeline within three minutes of the leak. Line 5 resumed service Sept. 13. The report states that systems monitoring the pipeline were operating when the incident occurred. However, Soine wrote the company’s leak detection system did not trigger because of the immediate shutdown of Line 5.

The company reported the incident to the National Response Center an hour later at 11:02 a.m. The Wisconsin Department of Natural Resources has said its spills hotline received notification at 11:15 a.m.

Enbridge said wildlife and water have not been affected.

“Community air monitoring is ongoing and has consistently shown safe air quality outside of the incident site. Monitoring wells continue to show no contamination, and soil and water monitoring remains ongoing,” Enbridge spokesperson Juli Kellner said.

The company plans to test, remove and properly dispose of soil from the excavation area.

A PHMSA spokesperson said the agency’s investigation remains ongoing. Texas-based Stress Engineering Services will conduct a mechanical and metallurgical analysis of the failed section of pipe. The agency’s accident investigation team will also inspect the truck. Inspectors are in the region overseeing construction of the Line 5 reroute.

“PHMSA may pursue additional enforcement action if its investigation identifies any violations of federal pipeline safety regulations or if additional corrective actions are necessary,” a PHMSA spokesperson said.

WPR previously reported that federal accident data shows the leak is the company’s and state’s largest oil and gas pipeline spill in Wisconsin in more than 50 years.

Environmental advocates and the Bad River Band of Lake Superior Chippewa have called on Gov. Tony Evers and the DNR to do more in response to the leak, including calling for a disaster declaration and revocation of permits for Enbridge’s Line 5 reroute. They pointed to Michigan Gov. Gretchen Whitmer’s call for removal of Line 5 in the Straits of Mackinac, as well as a new regulatory review of Michigan permits issued for Enbridge’s tunnel project.

Neither the governor’s office nor the DNR has responded to those calls.

Line 5 carries up to 23 million gallons of crude oil and natural gas liquids daily from Superior to Sarnia, Ontario. The pipeline serves 10 refineries and propane facilities in the Midwest and Great Lakes region.

Enbridge built a temporary bypass to bring the pipeline back online amid objections from the Wisconsin DNR, which said the company lacked state approvals. Enbridge contends the construction complied with existing permits and an application for changes to its stormwater permit. A DNR spokesperson has said the agency continues to review options in response to the unpermitted construction.

Last week, fires damaged two company sites — an office building in Superior and drilling equipment at a Line 5 reroute site in Ashland County. The Federal Bureau of Investigation is leading a probe into both fires.

Roughly two-thirds of the $1 billion Line 5 reroute has been built. The project employs 700 workers. As many as a dozen other spills have occurred during the project, according to a court filing by the Bad River band.

In 2020, Enbridge proposed the reroute after the Bad River band sued the company in 2019 to shut down and remove the pipeline from tribal lands where easements had expired.

Three years ago, a federal judge found the company was trespassing and ordered Enbridge to pay roughly $5 million and shut down or reroute Line 5. The band and Enbridge appealed the decision. In August, a federal appeals panel ruled that Enbridge has been trespassing and must remove the pipeline from the Bad River reservation. However, the panel gave the company more time to complete the Line 5 reroute.

This story was originally published by WPR.

Enbridge estimates northern Wisconsin Line 5 gas leak will cost $15M is a post from Wisconsin Watch, a non-profit investigative news site covering Wisconsin since 2009. Please consider making a contribution to support our journalism.

❌