Is the Milwaukee I-94 construction project expected to take eight years?

Reading Time: < 1 minute

Wisconsin Watch partners withΒ GigafactΒ to produce Fact Briefs β€” bite-sized fact checks of trending claims. Read our methodology to learn how we check claims.

Yes.

The massive Interstate 94 construction project in Milwaukee County is expected to wrap up in 2033, according to a timeline on the state Department of Transportation’s project page.

Construction began on the I-94 East-West corridor in late 2025, meaning eight years will pass before utility and roadway construction are estimated to end in 2033.

Parts of the roughly $1.7 billion project will be completed earlier than 2033. The Stadium Interchange reconstruction will take about four years, for example.

The project covers 3 Β½ miles of I-94 between 16th and 70th Streets in Milwaukee County and prompted long-term closures of several roads.

Plans include widening the freeway from three to four lanes in each direction, eliminating left-turn ramps, redesigning the Stadium Interchange and reconstructing aging roads.Β 

Crash rates in the corridor are higher than the statewide average, and 13 bridges do not meet clearance standards, according to the DOT.

This fact brief is responsive to conversations such as this one.